Saturday, December 8, 2007

movin' along...


Insulation is going in and sheetrock is going up. It would have been nice if 100% insulation could be installed, followed by 100% sheetrock, but things seldom work the way they should on paper. The framing inspector called for some additional hurricane clips on the porch rafters, pushing back our insulation contractors by 2 days. Meanwhile, our sheetrockers had to get on the job because they're going out of town for another job early next week. So..since the sheetrockers were willing to work weekends, they and the insulation contractors can play leap frog on the schedule for a couple of days. They both should be done by Wednesday.

No comments: